IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI
Title
AN ORDINANCE appropriating $2,871,621.00 from the Undesignated Fund Balance of the 2022 County Improvement Fund and awarding a contract on Request for Proposals 7-22 for the design/build construction of the new Jackson County Detention Center to J.E. Dunn-Axiom of Kansas City, MO, at an initial Phase I cost to the County not to exceed $2,871,621.00, and declaring the intent of Jackson County to reimburse itself for this expense from future bond proceeds.
Intro
ORDINANCE NO. 5621, April 25, 2022
INTRODUCED BY Theresa Cass Galvin, County Legislator
Body
WHEREAS, after a two-phase nationwide procurement process for qualified design-build teams to design and construct a new 1,244-bed Jackson County Detention Center, consisting of RFQ 70-21 distributed to 500 firms, with two firms responding, and RFP 7-22, which resulted in an evaluation of the two detailed proposals by a selection committee consisting of representatives designated by the County Executive, County Legislature, Prosecuting Attorney, Sheriff, and 16th Circuit Court, the joint-venture of J.E. Dunn-Axiom of Kansas City (Jackson County), MO, has been recommended by the selection committee; and
WHEREAS, a multiple-phase Design/Build Agreement has been negotiated to cover the entire project; and,
WHEREAS, by this Ordinance, the Legislature takes up the approval of the preliminary maximum budget for the design and construction of the entire project, $256,500,000.00, and the funding of Phase I of the project, pre-design and preliminary construction services; and,
WHEREAS, after 120 days, the County will be presented with a preliminary design and a proposed guaranteed maximum price; and
WHEREAS, the cost of Phase 1 of the Design/Build Agreement, pre-design and preliminary construction services, is $2,871,621.00; and,
WHEREAS, an appropriation is necessary to place the funds required for this phase in the proper spending account; now theref...