Title: AN ORDINANCE appropriating $254,886.00 from the undesignated fund balance of the 2014 Special Road and Bridge Fund, authorizing the County Executive to execute Change Order No. 3 to the Cooperative Agreement with Motorola Solutions, Inc., at a cost savings to the County of $119,636.00, and authorizing Change Order No. 1 to the Agreement with Superior Bowen Asphalt for the furnishing of parking lot improvements to the new Sheriff's Headquarters, at a cost to the County not to exceed $254,886.00.
Sponsors: Dan Tarwater III
Indexes: CHANGE ORDER, COOPERATIVE AGREEMENT, SPECIAL ROAD & BRIDGE FUND
Attachments: 1. 4686adopt, 2. 4686CO.pdf, 3. 4686CO
Related files: 18561, 4591, 4471, 18551
IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI
 
 
Title
AN ORDINANCE appropriating $254,886.00 from the undesignated fund balance of the 2014 Special Road and Bridge Fund, authorizing the County Executive to execute Change Order No. 3 to the Cooperative Agreement with Motorola Solutions, Inc., at a cost savings to the County of $119,636.00, and authorizing Change Order No. 1 to the Agreement with Superior Bowen Asphalt for the furnishing of parking lot improvements to the new Sheriff's Headquarters, at a cost to the County not to exceed $254,886.00.
 
 
Intro
ORDINANCE NO. 4686, November 3, 2014
 
INTRODUCED BY Dan Tarwater, County Legislator
 
 
Body
WHEREAS, by Ordinance 4471, dated November 5, 2012, the Legislature authorized an Agreement with Motorola Solutions, Inc., of Schaumberg, IL, for the furnishing of a narrow band public service radio system, at an actual cost to the County of $4,838,855.00; and,
 
WHEREAS, by Ordinance 4591, dated November 25, 2013, the Legislature did authorize Change Order No. 1 to the Agreement with Motorola Solutions for installation of the radio system at the new Sheriff's Headquarters; and,
 
WHEREAS, BY Resolution 18561, dated June 26, 2014, the Legislature did authorize Change Order No. 2 to the Agreement with Motorola Solutions for the furnishing of an uninterrupted power supply to the radio system at the Sheriff's Headquarters; and,
 
WHEREAS, further modifications to the Scope of Work with Motorola Solutions have now reduced the cost of that Agreement; and,
 
WHEREAS, Motorola Solutions has requested the approval of Change Order No. 3 to its Agreement, extending the Agreement to February 27, 2015, and reducing the contract amount by $119,636.00; and,
 
WHEREAS, these funds are now available to be appropriated for other projects related to the new Sheriff's Headquarters; and,
 
WHEREAS, by Resolution 18551, dated June 19, 2014, the Legislature did award a contract to Superior Bowen Asphalt Company for the 2014 Road Maintenance Project, No. 3175; and,
WHEREAS, Superior Bowen had included in that bid an option for the Sheriff's Headquarters Parking Lot Improvements, but this item was not included in the contract authorized at that time due to funding constraints; and,
 
WHEREAS, the Director of Public Works now recommends Change Order No. 1 to the Agreement with Superior Bowen for improvements to the parking lot located at the new Sheriff's Headquarters, at an additional cost to not exceed $254,886.00; and,
 
WHEREAS, an appropriation is necessary to place the needed funds for the parking lot improvement in the appropriate spending account; and,
 
WHEREAS, the County Executive recommends said appropriation; now therefore,
 
BE IT ORDAINED by the County Legislature of Jackson County, Missouri, that the  following appropriation from the undesignated fund balance of the 2014 Special Road and Bridge Fund be and hereby is made:
DEPARTMENT/DIVISION            CHARACTER/DESCRIPTION       FROM       TO
 
Special Road and Bridge Fund
Non-Departmental
 
 
004-2810      Undesignated Fund Balance      $254,886
004-5104      58020 - Buildings & Improvements      $254,886
 
and,
 
 
 
BE IT FURTHER ORDAINED that the County Executive be and hereby is authorized to execute the attached Change No. 3 to the Cooperative Agreement with Motorola Solutions, Inc., and Change Order No. 1 to the contract with Superior Bowen Asphalt Company for Public Works Project No. 3175; and,
 
 
BE IT FURTHER RESOLVED that the Director of Finance and Purchasing is authorized to make all payments, including final payment on the contracts.
 
 
 
Enacted and Approved
Effective Date:  This ordinance shall be effective immediately upon its signature by the County Executive.
 
APPROVED AS TO FORM:
 
 
____________________________            _____________________________
Chief Deputy County Counselor                  County Counselor
 
      I hereby certify that the attached Ordinance, Ordinance No. 4686 introduced on November 3, 2014, was duly passed on November 3, 2014 by the Jackson County Legislature.  The votes thereon were as follows:
 
 
      Yeas _______7_______                  Nays ______1______
 
 
      Abstaining ___0_______                  Absent _____1______
 
 
This Ordinance is hereby transmitted to the County Executive for his signature.
 
 
 
____________________                        ________________________________
Date                                          Mary Jo Spino, Clerk of Legislature
 
 
I hereby approve the attached Ordinance No. 4686.
 
 
 
____________________                        ________________________________
Date                                          Michael D. Sanders, County Executive
 
 
Fiscal Note
Funds sufficient for this appropriation are available from the source indicated below.
 
ACCOUNT NUMBER:      004      2810
ACCOUNT TITLE:            Special Road and Bridge Fund
                        Undesignated Fund Balance
NOT TO EXCEED:            $254,886.00
 
 
 
 
 
There is a balance otherwise unencumbered to the credit of the appropriation to which the expenditure is chargeable and there is a cash balance otherwise unencumbered in the treasury to the credit of the fund from which payment is to be made each sufficient to provide for the obligation herein authorized.
 
ACCOUNT NUMBER:      004      5104 58020
ACCOUNT TITLE:            Special Road and Bridge Funds
                        Non-Departmental      
                        Buildings & Improvements
NOT TO EXCEED:            $254,886.00
 
 
 
 
______________________                  _______________________________
Date                                          Director of Finance and Purchasing