File #: 20802    Version: Name: Design-Build criteria Detention Center
Type: Resolution Status: Passed
File created: 10/28/2021 In control: Public Works Committee
On agenda: 11/1/2021 Final action: 11/8/2021
Title: A RESOLUTION setting out the procedure by which Jackson County will select and procure a Design-Builder for the construction of a new Jackson County Detention Center, as authorized by section 67.5060, RSMo.
Sponsors: Theresa Cass Galvin
Attachments: 1. 20802bu.pdf, 2. 20802adopt.pdf
Related files: 5561
IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI

Title
A RESOLUTION setting out the procedure by which Jackson County will select and procure a Design-Builder for the construction of a new Jackson County Detention Center, as authorized by section 67.5060, RSMo.


Intro
RESOLUTION NO. 20802, November 1, 2021

INTRODUCED BY Theresa Cass Galvin, County Legislator


Body
WHEREAS, Jackson County is a home rule charter county, organized pursuant to article VI, section 18 of the Constitution of Missouri; and,

WHEREAS, Jackson County, pursuant to article III, section 6.2 of the Jackson County Charter, adopted a procurement procedure for Design-Build services by Executive Order 94-24, dated October 6, 1994; and,

WHEREAS, the Design-Build procedure adopted by the County pursuant to its home rule charter is over twenty-seven years old; and,

WHEREAS, the Legislature desires to contract with a Design-Builder for the construction of a new Jackson County Detention Center on a tract of land previously acquired for this purpose; and,

WHEREAS, any county operating under home rule charter pursuant to article VI, section 18 of the Constitution of Missouri may adopt a Design-Build construction process via ordinance, rule, or regulation pursuant to section 67.506(21), RSMo; and,

WHEREAS, the County will establish and follow the process set forth herein to select a Design-Builder utilizing a qualification-based methodology: a) the County will issue a request for qualifications (RFQ); b) the County will receive, evaluate, and score the proposals submitted; c) the County will establish a "short list" of no more than three (3) of the best qualified firms that submitted RFQ's; d) upon establishing a short list, the County will issue a request for proposals (RFP) to each entity selected per the RFQ process; e) the County will issue a request for a cost proposal from each entity selected per the RFQ process, which cost proposal shall include contractor fees, contractor overhe...

Click here for full text