File #: 19453    Version: 0 Name: Change Order No. 1 Little Blue Trace Trail Extension, Phase One Project No. 3208
Type: Resolution Status: Passed
File created: 4/13/2017 In control: Land Use Committee
On agenda: 4/17/2017 Final action: 4/24/2017
Title: A RESOLUTION authorizing Change Order No. 1 to the contract with Pyramid Contractors, Inc., of Olathe, KS, for the Little Blue Trace Trail Extension, Phase One, Project No. 3208, increasing the contract amount by $261,134.00.
Sponsors: Tony Miller
Indexes: CHANGE ORDER, CONTRACT, LITTLE BLUE TRACE PARK
Attachments: 1. 19453bu.pdf, 2. 19453adopt, 3. 19453-CHGEODRNO1-PYRMDCONTINC
Related files: 17650, 4793, 19329
IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI


Title
A RESOLUTION authorizing Change Order No. 1 to the contract with Pyramid Contractors, Inc., of Olathe, KS, for the Little Blue Trace Trail Extension, Phase One, Project No. 3208, increasing the contract amount by $261,134.00.


Intro
RESOLUTION NO. 19453, April 17, 2017

INTRODUCED BY Tony Miller, County Legislator


Body
WHEREAS, by Resolution 17650, dated August 22, 2011, the Legislature did authorize the execution of a Cooperative Agreement with the City of Kansas City, Missouri, to provide for the extension of the Little Blue Trace Trail between Lee's Summit Road and Longview Lake; and,

WHEREAS, by Ordinance 4793, dated November 9, 2015, the Legislature did appropriate funds in the amount of $675,000.00 received from the City of Kansas City, Missouri, to cover the costs of its portion of the Little Blue Trace Trail Extension, Phase One, Project No. 3208; and,

WHEREAS, by Resolution 19329, dated December 5, 2016, the Legislature did award a contract on Bid No. PW 11-2016 for the Little Blue Trace Trail Extension, Phase One, Project No. 3208 to Pyramid Contractors, Inc., of Olathe, KS, at a cost to the County not to exceed $813,249.15, including a five percent contingency; and,

WHEREAS, the Director of Parks + Rec recommends Change Order No. 1 to the Agreement with Pyramid Contractors, Inc., to include additional drainage, grading, and paving for the project, increasing the contract amount by $261,134.00; and,

WHEREAS, this additional work will extend the project completion date from July 1, 2017, to August 31, 2017; now therefore,

BE IT RESOLVED by the County Legislature of Jackson County, Missouri, that Change Order No. 1 to the aforesaid contract be, and is hereby, approved, and the County Executive be, and is hereby authorized to execute said change order on behalf of the County; and,

BE IT FURTHER RESOLVED that the Director of Finance and Purchasing is authorized to make all payments,...

Click here for full text