File #: 18161    Version: 0 Name: Historic Truman Courthouse (Universal Construction)
Type: Resolution Status: Passed
File created: 5/6/2013 In control: Finance and Audit Committee
On agenda: 5/6/2013 Final action: 5/13/2013
Title: A RESOLUTION authorizing Change Order No. 2 to the contract with Universal Construction of Lenexa, KS, for the Historic Truman Courthouse, Project No. 3147, increasing the contract amount by $199,556.00.
Sponsors: Dennis Waits
Indexes: CHANGE ORDER, HISTORIC TRUMAN COURTHOUSE
Attachments: 1. 18161adopt.pdf, 2. 18161CO.pdf
Related files: 18639
IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI


Title
A RESOLUTION authorizing Change Order No. 2 to the contract with Universal Construction of Lenexa, KS, for the Historic Truman Courthouse, Project No. 3147, increasing the contract amount by $199,556.00.


Intro
RESOLUTION NO. 18161, May 6, 2013

INTRODUCED BY Dennis Waits, County Legislator


Body
WHEREAS, by Resolution 18028, dated November 19, 2012, the Legislature did authorize an agreement with Universal Construction of Lenexa, KS, for the renovation of the Historic Truman Courthouse, Project No. 3147, at a cost to the County not to exceed $4,800,000.00; and,

WHEREAS, by Resolution 18118, March 11, 2013, the Legislature did authorize Change Order No. 1 to the agreement with Universal Construction in the amount of $85,026.00, related to improvements for the City of Independence's Tourism Department Offices; and,

WHEREAS, the contractor has now determined that a large portion of the waste pipe in the building has excessive leaks and/or wear and will need to be replaced; and,

WHEREAS, additionally, the contractor has requested additional working days to complete this extra work by the target completion date prior to the Santa-Cali-Gon Days festival, and requests an allowance to cover overtime wage rates only; and,

WHEREAS, the original plans proposed basic signage on the building grounds, but it is now recommended that the signage be upgraded to better represent the historic dignity of the building; and,

WHEREAS, Change Order No. 2 in the amount of $199,556.00 is needed to provide additional funds to cover the costs of these improvements and overtime costs; and,

WHEREAS, the Director of Public Works recommends approval of the request; and,

WHEREAS, this project is in the best interest of the health, safety, and welfare of the citizens of Jackson County; now therefore,

BE IT RESOLVED by the County Legislature of Jackson County, Missouri, that Change Order No. ...