IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI
Title
A RESOLUTION authorizing the County Executive to execute Change Order No. 2 to the contract awarded to Jenkins & Associates, Inc., of Shawnee Mission, KS, for office building alterations at the Public Works Department New Technology Center, at a cost to the County not to exceed $16,809.00, for a total cost not to exceed $272,697.00 and increasing the estimated construction time from ninety (90) working days to ninety-eight (98) working days.
Intro
RESOLUTION # 15281, November 29, 2004
INTRODUCED BY Bob Spence, County Legislator
Body
WHEREAS, by Resolution 15112, dated July 26, 2004, the Legislature did award a contract on Bid No. 19-04 to Jenkins & Associates, Inc., of Shawnee Mission, KS, for office building alterations at the Public Works Department New Technology Center, at an initial cost to the County not to exceed $227,922.00; and,
WHEREAS, by Resolution 15176, dated September 27, 2004, the Legislature approved Change Order No. 1 to the aforesaid contract in the additional amount of $27,966.00 for a total charge cost to the County of $255,888.00; and,
WHEREAS, Change Order No. 2 to the aforesaid contract, a copy of which is attached hereto, is necessary to add to this project the cost of changes and additional items referenced in the Jenkins & Associates proposal dated November 16,2004, at an increased cost to the County not to exceed $16,809.00 and to increase the estimated construction time from ninety (90) working days to ninety-eight (98) working days at a total cost to the County not to exceed $272,697.00; now therefore,
BE IT RESOLVED by the County Legislature of Jackson County, Missouri, that Change Order No. 2 to the aforesaid contract is hereby approved at a cost not to exceed $16,809.00 for a total cost to the County not to exceed $272,697.00 and increasing the estimated construction time to ninety-eight (98) working days, and the County Executive is auth...