File #: 15211    Version: 0 Name: 2004 Pavement Maintenance Project.
Type: Resolution Status: Passed
File created: 11/1/2004 In control: Public Works Committee
On agenda: 11/1/2004 Final action: 11/8/2004
Title: A RESOLUTION authorizing Change Order No. 1 (Final) to the contract with Musselman and Hall Contractors of Kansas City, MO, for the 2004 Pavement Maintenance Project (Phase 6), No. 3019, reducing the contract amount by $6,436.65 for a revised total cost to the County of $96,391.35.
Sponsors: Bob Spence
Indexes: CHANGE ORDER, PAVEMENT MAINTENANCE
IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI


Title
A RESOLUTION authorizing Change Order No. 1 (Final) to the contract with Musselman and Hall Contractors of Kansas City, MO, for the 2004 Pavement Maintenance Project (Phase 6), No. 3019, reducing the contract amount by $6,436.65 for a revised total cost to the County of $96,391.35.


Intro
RESOLUTION # 15211, November 1, 2004

INTRODUCED BY Bob Spence, County Legislator


Body
WHEREAS, the County did, by Resolution 15061, dated June 21, 2004, enter into a contract with Musselman and Hall Contractors of Kansas City, MO, in the actual amount of $102,828.00, for the 2004 Pavement Maintenance Project (Phase 6), No. 3019; and,

WHEREAS, the proposed Change Order No. 1 (Final), a copy of which is attached hereto and incorporated herein by reference, is necessary to adjust various plan quantities to as-built quantities, and said change order will result in a decrease of $6,436.65; therefore,

BE IT RESOLVED by the County Legislature of Jackson County, Missouri, that Change Order No. 1 (Final) to the aforesaid contract with Musselman and Hall Contractors of Kansas City, MO, in the amount of $96,391.35, is approved and the County Executive is authorized to execute the change order on behalf of the County; and,

BE IT FURTHER RESOLVED that the Director of the Department of Finance is authorized to make all payments, including final payment on the contract; and,
BE IT FURTHER RESOLVED that the Director of the Department of Finance is authorized to release the encumbrance on the contract balance.

Enacted and Approved
Effective Date: This Resolution shall be effective immediately upon its passage by a majority of the Legislature.

APPROVED AS TO FORM:


____________________________ ___________________________________
Acting Chief Deputy County Counselor County Counselor

Certificate of Passage

I hereby certify that the attached resolution, Resolution # 15211 of Novem...

Click here for full text