File #: 16310    Version: 0 Name: Second Addendum to the Cooperative Agreement with the City of Independence
Type: Resolution Status: Passed
File created: 6/4/2007 In control: Public Works Committee
On agenda: 6/4/2007 Final action: 6/11/2007
Title: A RESOLUTION authorizing the County Executive to execute a Second Addendum to the Cooperative Agreement with the City of Independence, MO, to reallocate funds in connection with the 39th Street (Noland to Lee's Summit), 39th Street (Noland to Crysler), 35th & Noland Road, Truman Road (M-291 to Swope), and R.D. Mize (Little Blue Parkway to Eureka) public improvement projects, at no additional cost to the County.
Sponsors: Bob Spence
Indexes: COOPERATIVE AGREEMENT, ROAD & BRIDGE REPLACEMENT
IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI


Title
A RESOLUTION authorizing the County Executive to execute a Second Addendum to the Cooperative Agreement with the City of Independence, MO, to reallocate funds in connection with the 39th Street (Noland to Lee's Summit), 39th Street (Noland to Crysler), 35th & Noland Road, Truman Road (M-291 to Swope), and R.D. Mize (Little Blue Parkway to Eureka) public improvement projects, at no additional cost to the County.


Intro
RESOLUTION # 16310, June 4, 2007
INTRODUCED BY Bob Spence, County Legislator

Body
WHEREAS, by Ordinance 3657, dated August 8, 2005, the Legislature did appropriate proceeds of the Series 2005 Public Building Corporation Leasehold Revenue Bonds for various capital improvement projects throughout the County; and,

WHEREAS, by Resolution 15892, dated May 15, 2006, the Legislature did authorize the County Executive to execute a Cooperative Agreement and Addendum with the City of Independence, MO, in connection with the 39th Street (Noland to Lee's Summit), 39th Street (Noland to Crysler), 35th & Noland Road, Truman Road (M-291 to Swope), and R.D. Mize (Little Blue Parkway to Eureka) public improvement projects, at a total cost to the County not to exceed $4,000,000.00; and,

WHEREAS, the City has requested and the Director of Public Works now recommends that the funds for the implementation of these projects, be reallocated within the projects as set forth below:
Project Original Amount Modified Amount Revised Total

#3036 $900,000.00 - $900,000.00 - 0 -
39th Noland to Crylser

#3033 & 3061 $900,000.00 $900,000.00 $1,800,000.00
39th Lee's Summit to Noland

#3035 $200,000.00 $ 86,818.93 $ 286,818.93
35th and Noland intersection

#3034 $800,000.00 $ 40,959.05 $ 840,959.05
Truman Rd Hwy 291 to Vista

#3013 $400,000.00 - $ 399,730.77 $ 269.23
R.D. Mize Necessary to Eureka

#3094 $800,000.00 $ 271,952.79 $1...