File #: 3150    Version: 0 Name: Communication tower amendment to permit.
Type: Ordinance Status: Passed
File created: 5/30/2001 In control: Land Use Committee
On agenda: Final action: 6/11/2001
Title: AN ORDINANCE approving an amendment to an existing conditional use permit to operate a 147-foot monopole commercial communication tower, as to a certain 0.08 ± acre tract.
Indexes: USE PERMIT
IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI


Title
AN ORDINANCE approving an amendment to an existing conditional use permit to operate a 147-foot monopole commercial communication tower, as to a certain 0.08 ± acre tract.


Intro
ORDINANCE 3150, May 30, 2001


Body
BE IT ORDAINED by the County Legislature of Jackson County, Missouri as follows:

Section 1. An amendment to an existing conditional use permit, to expire July 6, 2024, to operate a 147-foot monopole commercial communication tower, subject to restrictions specified, under the Unified Development Code, is hereby approved as to a certain tract of land described as follows:
Description: The monopole commercial communication tower is located on a 0.08 acre tract of land generally located north of Stark Avenue on the west side of Blue Ridge Blvd. lying in the southeast quarter of Section 6, Township 49, Range 32 in Jackson County, Missouri and more specifically described in Attachment to RLA.

Section 2. The amended conditional use permit granted by this ordinance is subject to the

following conditions:

1. The commercial monopole tower shall not exceed a height of 150 feet.

2. The monopole tower and appurtenance shall be installed according to manufacturers specifications using sound engineering and safety practices.

3. The building permit application shall include an engineering report specifying the following information:


a. Detailed structural plans for the tower signed and sealed by a Missouri Registered Engineer; and

b. Engineer's certification that anticipated levels of electro magnetic radiation to be generated by facilities on the site, including the effective radiated power (ERP) on the antenna shall be within the guidelines established by the Federal Communications Commission (FCC).


4. The access driveway to compound area will need to be concrete surface 8 inches thick within right-of-way and 4 inches thick outside of right-of-way (prop...

Click here for full text