AN ORDINANCE appropriating $2,500,000.00 from the undesignated fund balance of the 2024 County Improvement Fund, transferring $2,500,000.00 within the 2024 New Detention Center C/P Fund, and authorizing the County Executive to execute an amendment to the contract with J.E. Dunn-Axiom of Kansas City, MO, for the construction of the new Jackson County Detention Center to cover Component Packages 3 and 4 related to the final design, construction, and furnishing costs of the new Detention Center Project, at a cost to the County not to exceed $19,698,551.00.
Intro
ORDINANCE NO. 5875, August 12, 2024
INTRODUCED BY Jeanie Lauer, County Legislator
Body
WHEREAS, by Ordinance No. 5621, dated April 25, 2022, the Legislature did award a contract for the construction of the new Jackson County Detention Center to J.E. Dunn-Axiom of Kansas City (Jackson County), MO pursuant to the terms and conditions of Request for Proposals No. 7-22; and,
WHEREAS, by Ordinance No. 5732, dated April 17, 2023, the Legislature did authorize the issuance of special obligation bonds for the funding of the new Jackson County Detention Center; and,
WHEREAS, by Ordinance No. 5743, dated May 9, 2023, the Legislature did authorize Component Package 2 (Site Demolition, Site Development, and Earthwork), and Component Package 2a (Engineering, Detailing, Mockups, and Early Procurement) to begin construction of the new Detention Center; and,
WHEREAS, by Resolution No. 21512, dated January 22, 2024, the Legislature did authorize Component Packages 2B and 2C related to the furnishing of services, labor and materials for the footing, foundation, and structural portions of the Detention Center Project; and,
WHEREAS, it is now appropriate to approve Component Packages 3 and 4 related to the final design, construction, and furnishing costs; and,
WHEREAS, an appropriation and transfer are necessary to place the funds required to implement t...