IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI
Title
A RESOLUTION authorizing Change Order No. 3 (Final) to the contract with Superior-Bowen Asphalt Company of Kansas City, MO, for the 1997 Road Reconstruction and Rehabilitation Project, No. 2348, decreasing the contract amount by $11,193.84.
Intro
RESOLUTION #12384, October 5, 1998
INTRODUCED BY John C. Graham, County Legislator
Body
WHEREAS, the County did, by Resolution 11808, dated June 23, 1998, enter into a contract with Superior-Bowen Asphalt Company of Kansas City, MO, in the amount of $1,342,716.10, for the 1995 Road Surface Rehabilitation Project, No. 2320; and,
WHEREAS, subsequent change orders have adjusted the contract amount to the current authorization of $1,358,332.16; and,
WHEREAS, the proposed Change Order No. 3 (Final), a copy of which is attached hereto and incorporated herein by reference, is necessary to adjust all plan quantities to as-built quantities, and said change order will result in a decrease of $11,193.84 in the contract amount; therefore,
BE IT RESOLVED by the County Legislature of Jackson County, Missouri, that Change Order No. 3 to the aforesaid contract is approved and the County Executive is authorized to execute the change order on behalf of the County; and,
BE IT FURTHER RESOLVED that the Director of the Department of Finance is authorized to make all payments, including final payment on the contract...Attorney
Effective Date: This Resolution shall be effective immediately upon its passage by a majority of the Legislature.
APPROVED AS TO FORM:
_________________________ _________________________________
County Counselor
Certificate of Passage
I hereby certify that the attached resolution, Resolution #12384 of October 5, 1998, was duly passed on _______October 13___________, 1998 by the Jackson County Legislature. The votes thereon were as follows:
Yeas _______7__________ Nays ______0________
...
Click here for full text