IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI
Title
Appropriating $9,279.00 from the unappropriated surplus of the 1995 County Urban Road System Fund and authorizing the Public Works Director to execute Change Order No. 5 to the contract with Superior-Bowen Asphalt Company of Kansas City, MO, for the 1994 Road Rehabilitation Program, Project No. 2296, increasing the contract amount by $9,278.50.
Intro
ORDINANCE #2420, June 5, 1995
INTRODUCED BY Victor E. Callahan, County Legislator
Body
WHEREAS, the County did, by Resolution 10398, dated July 11, 1994, enter into a contract with Superior-Bowen Asphalt Company of Kansas City, MO, in the amount of $1,600,163.08, for the 1994 Road Rehabilitation Program, Project No. 2296; and,
WHEREAS, subsequent change orders have increased the amount of the contract to $1,250,124.94; and,
WHEREAS, proposed Change Order No. 5, a copy of which is attached hereto and incorporated herein by reference, is necessary to adjust all variable contract quantities as set forth in the o iginal contract, and said change order will result in an increase of $9,278.50; therefore,
BE IT ORDAINED by the County Legislature of Jackson County, Missouri, that the following appropriation be made from the unappropriated surplus of the 1995 County Urban Road System Fund to cover the cost of Change Order No. 5 as follows:
DEPARTMENT/DIVISION CHARACTER/DESCRIPTION FROM TO
Unappropriated Surplus $9,279 Div. of Administration Public Works Dept. County Urban Road System Lee's Summit City Projects $9,279
and,
BE IT FURTHER ORDAINED that Change Order No. 5 to the aforesaid contract is approved and the Director of Public Works is authorized to execute the change order on behalf of the County; an ,
BE IT FURTHER ORDAINED that the Manager of the Division of Finance be and hereby is authorized to make all payments including final payment on the...
Click here for full text