File #: 12887    Version: 0 Name: Change Order #18 - Walton Construction
Type: Resolution Status: Passed
File created: 9/20/1999 In control: (R)Health and Justice Committee
On agenda: Final action: 10/4/1999
Title: A RESOLUTION authorizing Change Order No. 18 to the contract with Walton Construction Co. of Kansas City, MO (Bid No. PW-2345, Bid Package No. 8), for various changes required in connection with general construction for the expansion at the Jackson County Detention Center, increasing the contract amount by $115,773.00.
Sponsors: Terry Young
Indexes: CHANGE ORDER, DETENTION CENTER
IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI
Title
A RESOLUTION authorizing Change Order No. 18 to the contract with Walton Construction Co. of Kansas City, MO (Bid No. PW-2345, Bid Package No. 8), for various changes required in connection with general construction for the expansion at the Jackson County Detention Center, increasing the contract amount by $115,773.00.

Intro
RESOLUTION #12887, September 20, 1999

INTRODUCED BY Terry Young, County Legislator

Body
WHEREAS, the County did, by Resolution 11712, dated April 14, 1997, enter into a contract with Walton Construction Co., Inc., in the actual amount of $6,762,426.00, and authorized additional expenditures to be approved by the County Executive at a cost not to exceed $338,121.00, for a total amount not to exceed $7,100,547.00, for general construction for the expansion at the Jackson County Detention Center; and,

WHEREAS, the County Executive and/or Legislature have approved Change Orders 1 through 17 for a total of $720,304.00, adjusting the contract amount to the current authorization of $7,482,730.00; and,

WHEREAS, the Legislature's Health and Justice Committee was advised on May 17, 1999, that there would be an additional/final change order(s) estimated at $150,000.00; and,

WHEREAS, the proposed Change Order No. 18, a copy of which, including Exhibit A, a detailed summary of changes, is attached hereto and incorporated herein by reference, is necessary due to miscellaneous contract changes and additions, and said change order will result in an increase not to exceed $115,773.00, respectively, for a new total cost not to exceed $7,598,503.00;

WHEREAS, the County has been advised by its Construction Manager that there will be one remaining/final change order totaling $29,778.00 so that the cost of all change orders to this bid package after May 17, 1999, will be less than the estimate of $150,000.00; therefore,