WHEREAS, by Resolution 16349, dated July 9, 2007, the County did award a contract for the 2007 Pavement Maintenance Phase 2, Micro-Surfacing Project, No. 3100, to Vance Brothers, Inc., of Kansas City, MO, at an actual cost to the County not to exceed $272,084.80; and,
WHEREAS, the project is now complete, and has been accepted by the Director of Public Works, such that final payment is now due and owing; now therefore,
BE IT RESOLVED by the County Legislature of Jackson County, Missouri, that the Director of Finance and Purchasing be and hereby is authorized to make final payment on the contract with Vance Brothers, Inc., of Kansas City, MO, for the 2007 Pavement Maintenance Phase 2, Micro-Surfacing Project, No. 3100.
Enacted and Approved
Effective Date: This Resolution shall be effective immediately upon its passage by a majority of the Legislature.
APPROVED AS TO FORM:
______________________________ ________________________________
Chief Deputy County Counselor County Counselor
Certificate of Passage
I hereby certify that the attached resolution, Resolution #16724 of October 6, 2008, was duly passed on October 13, 2008 by the Jackson County Legislature. The votes thereon were as follows:
Yeas ________9_________ Nays ______0________
Abstaining _____0________ Absent _____0_______
______________________ _________________________________
Date Mary Jo Spino, Clerk of Legislature
Fiscal Note
Funds sufficient for this expenditure were previously encumbered f...
Click here for full text