File #: 16311    Version: 0 Name: Change Order No. 2 to the Agreement with R.A. Knapp Construction, Inc.
Type: Resolution Status: Passed
File created: 6/4/2007 In control: Public Works Committee
On agenda: 6/4/2007 Final action: 6/11/2007
Title: A RESOLUTION authorizing the County Executive to execute Change Order No. 1 to the Agreement with R.A. Knapp Construction, Inc., of Kansas City, KS, for the Courtney-Atherton Road Bridge Replacement Project, No. 3007, at an additional cost to the County not to exceed $9,265.26.
Sponsors: Bob Spence
Indexes: CHANGE ORDER, R.A. KNAPP CONSTRUCITON, INC, ROAD & BRIDGE REPLACEMENT
IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI


Title
A RESOLUTION authorizing the County Executive to execute Change Order No. 1 to the Agreement with R.A. Knapp Construction, Inc., of Kansas City, KS, for the Courtney-Atherton Road Bridge Replacement Project, No. 3007, at an additional cost to the County not to exceed $9,265.26.


Intro
RESOLUTION # 16311, June 4, 2007

INTRODUCED BY Bob Spence, County Legislator


Body
WHEREAS, by Resolution 16189, dated March 5, 2007, the County did award a contract on Bid No. PW09-2006 for the Courtney-Atherton Road Bridge Replacement Project, No. 3007, to R.A. Knapp Construction, Inc., of Kansas City, KS, at a total cost to the County not to exceed $431,093.65; and,

WHEREAS, Change Order No. 1 is necessary to cover an increase in subcontractor bid quotes due to an extended award period of four months, and said change order will result in an increase to the contract in an amount not to exceed $9,265.26; now therefore,

BE IT RESOLVED by the County Legislature of Jackson County, Missouri, that the County Executive be and hereby is authorized to execute Change Order No. 1 to the agreement with R.A. Knapp Construction, Inc., of Kansas City, KS, for the Courtney-Atherton Road Bridge Replacement Project, No. 3007, in a form to be approved by the County Counselor; and,

BE IT FURTHER RESOLVED the Director of Finance and Purchasing is authorized to make all payments, except final payment on the contract, and change order.

Enacted and Approved
Effective Date: This Resolution shall be effective immediately upon its passage by a majority of the Legislature.

APPROVED AS TO FORM:

______________________________ ________________________________
Chief Deputy County Counselor County Counselor

Certificate of Passage

I hereby certify that the attached resolution, Resolution # 16311 of June 4, 2007, was duly passed on June 11, 2007 by the Jackson County Legislature. The vot...