File #: 17974    Version: 0 Name: ROW temporary construction easements and compensation for damages
Type: Resolution Status: Passed
File created: 9/10/2012 In control: County Legislature
On agenda: 9/10/2012 Final action: 9/10/2012
Title: A RESOLUTION authorizing payment to certain property owners, in the aggregate amount of $291,821.47, for the acquisition of right-of-way and temporary construction easements, and compensation for related damages in connection with the Lee's Summit Road Improvements Project, No. 3122.
Sponsors: Bob Spence
Indexes: EASEMENTS, LEE'S SUMMIT ROAD, RIGHT-OF-WAY
Attachments: 1. 17974adopt.pdf
IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI


Title
A RESOLUTION authorizing payment to certain property owners, in the aggregate amount of $291,821.47, for the acquisition of right-of-way and temporary construction easements, and compensation for related damages in connection with the Lee's Summit Road Improvements Project, No. 3122.


Intro
RESOLUTION #17974, September 10, 2012

INTRODUCED BY Bob Spence, County Legislator


Body
WHEREAS, by Resolution 16911, dated May 18, 2009, the Legislature did authorize the Director of Public Works to execute a Memorandum of Understanding with the cities of Kansas City, Missouri and Lee's Summit, Missouri, in connection to improvements to Lee's Summit Road between 40 Highway and Anderson Road; and,

WHEREAS, the Public Works Department is in the process of acquiring the needed right-of-ways, temporary construction easements, and estimating the related damages to property owners for the project; and,

WHEREAS, by Resolution 17824, dated February 27, 2012, the Legislature did authorize payments to property owners for six tracts, in a total amount of $122,034.55; and,

WHEREAS, by Resolution 17898, dated May 21, 2012, the Legislature did authorize payment to property owners for three additional tracts, in a total amount of $46,251.00; and,

WHEREAS, the Director of Public Works has made offers to and negotiated for three additional acquisitions of nine tracts for this project, listed below:
OWNER(S) TRACT(S) PRICE
Rainbow Development, LLC LS-16, LS-18, LS-22, LS-23, $248,781.04
LS-27, LS-27A, & LS-30

John R. Poland LS-39 $ 32,862.50

Country Meadows Baptist Church
of Independence, MO LS-50 $ 10,177.93

and,


WHEREAS, the Director of Public Works recommends payment to these property owners in an aggregate amount of $291,821.47 for the necessary right-of-ways, temporary construction easements, and related damages in furtherance of the Lee's Su...