File #: 20834    Version: 0 Name: RIR Change order #6
Type: Resolution Status: Passed
File created: 12/8/2021 In control: County Legislature
On agenda: 12/13/2021 Final action: 12/13/2021
Title: A RESOLUTION authorizing the County Executive to execute Change Order No. 6 to the contract with Radmacher Brothers Excavation Co., Inc., of Pleasant Hill, MO, for necessary changes to the construction of the Rock Island Shared Use Path Project, at an additional cost to the County not to exceed $25,719.40.
Sponsors: Tony Miller
Indexes: CHANGE ORDER, COUNTY EXECUTIVE, ROCK ISLAND RAIL CORRIDOR
Attachments: 1. 20834bu.pdf, 2. 20834adopt.pdf, 3. 20834 CO#6 Radmacher Bros - MODOT RIRC.pdf
Related files: 5231, 20451, 20576, 20699
IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI

Title
A RESOLUTION authorizing the County Executive to execute Change Order No. 6 to the contract with Radmacher Brothers Excavation Co., Inc., of Pleasant Hill, MO, for necessary changes to the construction of the Rock Island Shared Use Path Project, at an additional cost to the County not to exceed $25,719.40.


Intro
RESOLUTION NO. 20834, December 13, 2021

INTRODUCED BY Tony Miller, County Legislator


Body
WHEREAS, by Ordinance 5231, dated June 3, 2019, the Legislature did award a contract to Radmacher Brothers Excavation Co., Inc. of Pleasant Hill, MO, pursuant to Bid No. PW 09-2018, for the furnishing of construction services relating to the Rock Island Shared Use Path Project at a cost to the County not to exceed $11,067,439.71; and,

WHEREAS, subsequent change orders have increased the total contract price to its present authorization of $11,652,616.58; and,

WHEREAS, the cost adjustments in this Change Order are related to project changes made at the direction of County staff to successfully complete construction of the trail; and,

WHEREAS, the changes, based on need to match field conditions or resolve design issues, include the addition of three concrete sections of trail, limestone blocks for access control, and seeding and mulching due to insufficient quantities, and the deduction of fence quantities; and,

WHEREAS, a design change recommended by the contractor and other cost-reducing measures implemented by County staff have reduced the ultimate financial impact of these issues; and,

WHEREAS, a change order for these unforeseen conditions is necessary to build the project to the specified design, at an additional cost to the County not to exceed $25,719.40; and,

WHEREAS, Change Order No. 6, which addresses the retaining wall costs and cost-reducing measures, will bring the total not to exceed cost of the project to $11,678,335.98; and,

WHEREAS, no other contract changes are included i...