Title: A RESOLUTION awarding contracts on Bid No. 26-01 for the remaining construction of a road and bridge maintenance facility for use by the Public Works Department to Midwest Drywall Co., Inc., of Shawnee, KS ($325,700.00), Floor Decor Center, Inc., of Parkville, MO ($11,250.00), Desco Coating, Inc., of Olathe, KS ($8,902.00), FGI Glass Contracting, Inc., of Lee's Summit, MO ($70,240.00), Capital Painting Co. of Roeland Park, KS ($40,681.00), Cornell Roofing and Sheet Metal Co. of Independence, MO ($6,913.00), D. H. Pace Co., Inc., d/b/a Overhead Door Co. of North Kansas City, MO ($36,580.00), Anchor Sales and Service of Independence, MO ($81,739.00), National Fire Suppression, Inc., of Kansas City, KS ($29,990.00), Environmental Mechanical Contractors, Inc., of Olathe, KS ($823,870.00), and R.F. Fisher Electric Co., Inc., of Kansas City, KS ($477,672.00), in the actual aggregate amount of $1,913,537.00, and authorizing the County Executive to approve change orders in amounts not to exc...
Sponsors: Bill Petrie
Indexes: CHANGE ORDER, PUBLIC WORKS
IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI

Title
A RESOLUTION awarding contracts on Bid No. 26-01 for the remaining construction of a road and bridge maintenance facility for use by the Public Works Department to Midwest Drywall Co., Inc., of Shawnee, KS ($325,700.00), Floor Decor Center, Inc., of Parkville, MO ($11,250.00), Desco Coating, Inc., of Olathe, KS ($8,902.00), FGI Glass Contracting, Inc., of Lee's Summit, MO ($70,240.00), Capital Painting Co. of Roeland Park, KS ($40,681.00), Cornell Roofing and Sheet Metal Co. of Independence, MO ($6,913.00), D. H. Pace Co., Inc., d/b/a Overhead Door Co. of North Kansas City, MO ($36,580.00), Anchor Sales and Service of Independence, MO ($81,739.00), National Fire Suppression, Inc., of Kansas City, KS ($29,990.00), Environmental Mechanical Contractors, Inc., of Olathe, KS ($823,870.00), and R.F. Fisher Electric Co., Inc., of Kansas City, KS ($477,672.00), in the actual aggregate amount of $1,913,537.00, and authorizing the County Executive to approve change orders in amounts not to exceed 5% of the actual contract amounts, in an aggregate amount not to exceed $95,678.00, for a total aggregate cost not to exceed $2,009,215.00.

Intro
RESOLUTION 13732, June 18, 2001

INTRODUCED BY Bill Petrie, County Legislator


Body
WHEREAS, the Purchasing Director has solicited formal written bids under Bid No. 26-01 for the construction of a road and bridge maintenance facility for use by the Public Works Department; and,

WHEREAS, by Resolution 13705, dated May 21, 2001, the Legislature did award contracts for the construction of the first four bid packages of this project; and,

WHEREAS, the Purchasing Director has forwarded the bids received on the remaining bid packages to the Legislature for its determination in awarding contracts; and,

WHEREAS, the Legislature has determined that the following vendors have submitted the lowest and best bids for each remaining bid package:
Bid Package ...