File #: 15082    Version: 0 Name: Noland Road Bridge - Contract Change Order No. 2.
Type: Resolution Status: Passed
File created: 7/6/2004 In control: Public Works Committee
On agenda: 7/6/2004 Final action: 7/12/2004
Title: A RESOLUTION authorizing the County Executive to execute Change Order No. 2 and Change Order No. 3 to the contract with R. A. Knapp Construction of Kansas City, KS, for the Noland Road Bridge over Little Blue River Project, No. 2390, at an increased cost to the County not to exceed $27,390.75.
Sponsors: Bob Spence
Indexes: CHANGE ORDER, ROAD & BRIDGE MAINTENANCE
IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI


Title
A RESOLUTION authorizing the County Executive to execute Change Order No. 2 and Change Order No. 3 to the contract with R. A. Knapp Construction of Kansas City, KS, for the Noland Road Bridge over Little Blue River Project, No. 2390, at an increased cost to the County not to exceed $27,390.75.

Intro
RESOLUTION # 15082, July 6, 2004

INTRODUCED BY Bob Spence, County Legislator


Body

WHEREAS, by Resolution 14800, dated November 23, 2003, the Legislature did award a contract on Bid No. PW 03-2003 to R. A Knapp Construction of Kansas City, KS, for the Noland Road Bridge over Little Blue River Project, No. 2390, at an actual cost to the County of $1,229,837.10; and,

WHEREAS, by Resolution 14913, dated February 17, 2004, the Legislature did authorize Change Order No. 1 to the aforesaid contract, at an increased cost to the County of $9,246.00; and,

WHEREAS, Change Order No. 2 to the aforesaid contract, a copy of which is attached hereto, is necessary to add a barrier curb to the bridge approach slabs, at an increased cost to the County of $960.00; and,

WHEREAS, after field inspection by the geotechnical engineer, Change Order No. 3 to the aforesaid contract, a copy of which is attached hereto, is necessary to lower the rock sockets in order that the piers bear on sound rock, at an increased cost to the County of $26,430.75; now therefore,

BE IT RESOLVED by the County Legislature of Jackson County, Missouri, that Change Order No. 2 and Change Order No. 3 to the aforesaid contract is hereby approved and the County Executive is authorized to execute the change orders on behalf of the county; and,

BE IT FURTHER RESOLVED that the Director of the Department of Finance is authorized to make all payments, except final payment on the contract.

Enacted and Approved
Effective Date: This Resolution shall be effective immediately upon its passage by a majority of the Le...