File #: 15705    Version: 0 Name: Contract with J.M. Fahey Construction - Harry Truman Drive Extension Project.
Type: Resolution Status: Passed
File created: 11/21/2005 In control: Public Works Committee
On agenda: 11/21/2005 Final action: 11/28/2005
Title: A RESOLUTION awarding a contract on Bid No.PW01-2005 to J.M. Fahey Construction Company of Grandview, MO, for the Harry Truman Drive Extension Project #2999, at a cost to the County not to exceed $2,325,027.13.
Sponsors: Bob Spence
Indexes: HARRY S TRUMAN DRIVE
IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI

Title
A RESOLUTION awarding a contract on Bid No.PW01-2005 to J.M. Fahey Construction Company of Grandview, MO, for the Harry Truman Drive Extension Project #2999, at a cost to the County not to exceed $2,325,027.13.

Intro
RESOLUTION # 15705, November 21, 2005
INTRODUCED BY Bob Spence, County Legislator

Body
WHEREAS, by Resolution No. 14853, dated January 5, 2004, the Legislature did designate the improvement of Harry S. Truman Drive between 125th Street and Crystal Avenue as a County Urban Road System priority within the City of Grandview; and,

WHEREAS, pursuant to a Cooperative Agreement between the County and the City of Grandview, MO, the Director of Public Works solicited formal written bids under Bid No. PW01-2005 for the Harry Truman Drive Extension Project, #2999; and,

WHEREAS, he has received as the three lowest bids, bids from the following:
VENDOR COST
J.M. Fahey Construction Co. $2,325,027.13
Grandview, MO

L.B. Enterprizes Inc. $2,380,000.00
Belton, MO

Leavenworth Excavating & Equip. Co., $2,703,857.05
Leavenworth, KS
and,

WHEREAS, the Director of Public Works recommends that the contract award be made to J.M. Fahey Construction Co., of Grandview, MO, for the Harry Truman Drive Extension Project #2999 at a cost to the County not to exceed $2,325,027.13; now therefore,

BE IT RESOLVED by the County Legislature of Jackson County, Missouri that the award be made as recommended and that the County Executive be and hereby is authorized to execute any and all documents necessary to the accomplishment of the award; and,

BE IT FURTHER RESOLVED that the Director of the Department of Finance is authorized to make all payments, except final payment, on the contract; and,

BE IT FURTHER RESOLVED that the Director of Public Works be and hereby is authorized to approved adjustments in the contract line items, to the extent that no furth...