File #: 13006    Version: 0 Name: G-S Company contract change order #4.
Type: Resolution Status: Passed
File created: 1/3/2000 In control: (R)Health and Justice Committee
On agenda: 1/3/2000 Final action: 1/10/2000
Title: A RESOLUTION authorizing Change Order No. 4 (final) to the contract with The G-S Company of Baltimore, Maryland (Bid No. PW-2345, Bid Package No. 4), for various changes needed in connection with the construction of hollow metal doors and frames, finish, and detention hardware for the expansion at the Jackson County Detention Center, decreasing the contract amount by $7,916.40.
Sponsors: Lisa White Hardwick
Indexes: CHANGE ORDER, DETENTION CENTER
IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI


Title
A RESOLUTION authorizing Change Order No. 4 (final) to the contract with The G-S Company of Baltimore, Maryland (Bid No. PW-2345, Bid Package No. 4), for various changes needed in connection with the construction of hollow metal doors and frames, finish, and detention hardware for the expansion at the Jackson County Detention Center, decreasing the contract amount by $7,916.40.


Intro
RESOLUTION #13006, January 3, 2000

INTRODUCED BY Lisa White Hardwick, County Legislator


Body
WHEREAS, the County did, by Resolution 11539, dated December 9, 1996, enter into a contract with The G-S Company, in the actual amount of $416,994.00, and authorized additional expenditures approved by the County Executive at a cost not to exceed $21,000.00, for a total amount not to exceed $437,994.00, for the construction of hollow metal doors and frames, finish and detention hardware for the expansion at the Jackson County Detention Center; and,

WHEREAS, the County Executive has approved Change Orders 1, 2, and 3 for a total of $28,127.00, adjusting the contract amount to the current authorization of $445,121.00; and,

WHEREAS, the proposed Change Order No. 4 (final), a copy of which is attached hereto and incorporated herein by reference, is necessary due to miscellaneous contract changes and additions, and said change order will result in a decrease of $7,916.40; therefore,

BE IT RESOLVED by the County Legislature of Jackson County, Missouri, that Change Order No. 4 to the aforesaid contract is approved and the County Executive is authorized to execute the change order on behalf of the County; and,

BE IT FURTHER RESOLVED that the Director of the Department of Finance is authorized to make final payment on the contract, and to release the encumbrance on the contract balance of $7,916.40.