Title: A RESOLUTION awarding a contract on Bid No. PW-2345 (Bid Package No. 7A [rebid]) for the furnishing and installation of electrical and security systems for the expansion at the Jackson County Detention Center .
Sponsors: Dixie M. Flynn
Indexes: CONTRACT, DETENTION CENTER
IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI

Title
A RESOLUTION awarding a contract on Bid No. PW-2345 (Bid Package No. 7A [rebid]) for the furnishing and installation of electrical and security systems for the expansion at the Jackson County Detention Center .

Intro
RESOLUTION 11691, April 8, 1997


INTRODUCED BY Dixie M. Flynn, County Legislator

Body
WHEREAS, in connection with the Jackson County Detention Center expansion, the Purchasing Director has solicited formal written bids on Bid No. PW-2345 (Bid Package No. 7A [rebid]) for the furnishing and installation of electrical and security systems for the expansion at the Jackson County Detention Center; and,

WHEREAS, he has received as the lowest three bids thereon bids from the following:

ALTERNATE
BIDDER BASE BID No. 1 TOTAL BID

Mark One Electric Co., Inc. $1,949,322 $10,000 $1,959,322
Kansas City
(Jackson County), MO

Capital Electric $2,024,495 $14,500 $2,038,995
Construction Co., Inc.
Kansas City
(Jackson County), MO

R. F. Fisher Electric Co., $2,053,588 $4,499 $2,058,087
Inc.
Kansas City, KS

and,


WHEREAS, the Purchasing Director has recommended that award be made to Mark One Electric Co., Inc., of Kansas City, Missouri, for the reason that it has submitted the lowest and best bid; and,

WHEREAS, in the event that change orders to the contract become necessary, due to the time constraints involved in completion of this phase of work, it is appropriate that the County Executive be given authority to approve additional expenditures under this contract not to exceed 5% of the contract amount; therefore,

BE IT RESOLVED by the County Legislature of Jackson County, Missouri, that a contract on Bid No. PW-2345 (Bid Package No. 7A [rebid]) in the actual amount of $1,959,322.00, be awarded to Mark One Electric Co., Inc., of Kansas City, MO, as the lowest and best bidder; and,