File #: 12020    Version: 0 Name: Meyers Companies, Inc. Change Order.
Type: Resolution Status: Passed
File created: 1/26/1998 In control: Public Works Committee
On agenda: Final action: 2/2/1998
Title: A RESOLUTION authorizing Change Order No. 4 (Final) to the contract with Meyers Companies, Inc., of Stilwell, KS, for the Prospect Avenue Bridge and Intersection Improvements, Project No. 2139-2, decreasing the contract amount by $51,581.39.
Sponsors: John C. Graham
Indexes: CHANGE ORDER
Attachments: 1. Ord 2020.pdf
IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI

Title
A RESOLUTION authorizing Change Order No. 4 (Final) to the contract with Meyers Companies, Inc., of Stilwell, KS, for the Prospect Avenue Bridge and Intersection Improvements, Project No. 2139-2, decreasing the contract amount by $51,581.39.

Intro
RESOLUTION #12020, January 26, 1998

INTRODUCED BY John C. Graham, County Legislator

Body
WHEREAS, the County did, by Resolution 11182, dated February 20, 1996, enter into a contract with Meyers Companies, Inc., of Stilwell, KS, in the actual amount of $2,835,434.15, for the Prospect Avenue Bridge and Intersection Improvements, Project No. 2139-2; and,

WHEREAS, subsequent change orders have adjusted the contract amount to the current authorization of $2,824,879.25; and,

WHEREAS, the proposed Change Order No. 4 (Final), a copy of which is attached hereto and incorporated herein by reference, is necessary to adjust all variable contract quantities to as-built quantities, and will result in a decrease of $51,581.39 in the contract amount; and,

WHEREAS, all work contemplated in the original contract has been completed and is fully acceptable to the County; therefore,

BE IT RESOLVED by the County Legislature of Jackson County, Missouri, that Change Order No. 4 (Final) to the aforesaid contract be, and is hereby, approved and the Director of Public Works be, and is hereby authorized to execute the said change order on behalf of the County; and,

BE IT FURTHER RESOLVED that the Director of the Department of Finance be and hereby is authorized to make final payment on the contract, and to release the encumbrance on the contract balance of $51,581.39.
Attorney
Effective Date: This Resolution shall be effective immediately upon its passage by a majority of the Legislature.


APPROVED AS TO FORM: