IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI
Title
AN ORDINANCE appropriating $33,410.00 from the unappropriated surplus of the 2000 Criminal Justice Improvement Fund and authorizing Change Order No. 19 to the contract with Walton Construction Co. of Kansas City, MO (Bid No. PW-2345, Bid Package No. 8), for various changes required in connection with general construction for the expansion at the Jackson County Detention Center, increasing the contract amount by $33,410.00.
Intro
ORDINANCE #2986, January 10, 2000
INTRODUCED BY Terry Young, County Legislator
Body
WHEREAS, the County did, by Resolution 11712, dated April 14, 1997, enter into a contract with Walton Construction Co., Inc., in the actual amount of $6,762,426.00, and authorized additional expenditures to be approved by the County Executive at a cost not to exceed $338,121.00, for a total amount not to exceed $7,100,547.00, for general construction for the expansion at the Jackson County Detention Center; and,
WHEREAS, the County Executive and/or Legislature have approved Change Orders 1 through 18 for a total of $836,077.00, adjusting the contract amount to the current authorization of $7,598,503.00; and,
WHEREAS, the proposed Change Order No. 19, a copy of which is attached hereto and incorporated herein by reference, is necessary due to miscellaneous contract changes and additions, and said change order will result in an increase not to exceed $33,410.00, respectively, for a new total cost not to exceed $7,631,913.00; therefore,
BE IT ORDAINED by the County Legislature of Jackson County, Missouri, that the following appropriation be and hereby is made from the unappropriated surplus of the 2000 Criminal Justice Improvement Fund:
DEPARTMENT/DIVISION CHARACTER/DESCRIPTION FROM TO
Increased Revenue $33,410
012-2810 Unappropriated Surplus $33,410
012-2810 Unappropriated Surplus $33,410
Construction Program
012-2303-8020 Buildings...