File #: 15684    Version: 0 Name: Ideker, Inc.. Change Order #1 for the Colbern Road Phase II, Project No. 2411.
Type: Resolution Status: Passed
File created: 11/7/2005 In control: County Legislature
On agenda: 11/7/2005 Final action: 11/7/2005
Title: A RESOLUTION authorizing the County Executive to execute Change Order No. 1 with Ideker, Inc., of St. Joseph, MO, for the construction of Colbern Road Phase II, Project No. 2411 in an amount not to exceed $54,600.00
Sponsors: Bob Spence
Indexes: CHANGE ORDER, ROAD & BRIDGE MAINTENANCE
IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI

Title
A RESOLUTION authorizing the County Executive to execute Change Order No. 1 with Ideker, Inc., of St. Joseph, MO, for the construction of Colbern Road Phase II, Project No. 2411 in an amount not to exceed $54,600.00

Intro
RESOLUTION # 15684, November 7, 2005

INTRODUCED BY Bob Spence, County Legislator


Body
WHEREAS, the County did, by Resolution 15252, dated November 22, 2004, enter into a contract with Ideker, Inc., of St. Joseph, MO ("Ideker contract"), for the construction of Colbern Road Phase II, Project No. 2411, at a total cost to the County of $5,206,411.53; and,

WHEREAS, due to weather conditions and utility conflicts, construction has been delayed and extra crews and overtime are required in order to have the work completed by the end of November 2005; and,

WHEREAS, Change Order No. 1, a copy of which is attached hereto and incorporated herein by reference, encompasses this work acceleration and increases the contract amount by $54,600.00 for a new total cost of $5,261,011.53; and,

WHEREAS, the Acting Director of Public Works recommends execution of Change Order No. 1 and increasing the contract amount by $54,600.00; now therefore,

BE IT RESOLVED by the County Legislature of Jackson County, Missouri, that Change Order No. 1 to the Ideker contract be and hereby is approved and that the County Executive be and hereby is authorized to execute Change Order No. 1 in an amount not to exceed $54,600.00, for a new total cost of $5,261,011.53; and,

BE IT FURTHER RESOLVED that the Director of the Department of Finance is authorized to make all payments, except final payment, on the contract.



Enacted and Approved
Effective Date: This Resolution shall be effective immediately upon its passage by a majority of the Legislature.