IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI
Title
A RESOLUTION authorizing Change Order No. 1 (Final) to the contract with WCI, Inc. of Paola, KS, for the Harris Road Bridge Replacement Project, Federal Project BRO-048(44) #37300041, No. 2409, reducing the contract amount by $11,977.80 for a revised total cost to the County not to exceed $226,583.00.
Intro
RESOLUTION # 15327, January 3, 2005
INTRODUCED BY Bob Spence, County Legislator
Body
WHEREAS, the County did, by Resolution 14420, dated December 17, 2002, enter into a contract with WCI, Inc. of Paola, KS, in the actual amount of $238,580.80, for the Harris Road Bridge Replacement Project, Federal Project BRO-048(44) #37300041, No. 2409; and,
WHEREAS, the proposed Change Order No. 1 (Final), a copy of which is attached hereto and incorporated herein by reference, is necessary to adjust all plan quantities to as-built quantities, and said change order will result in a decrease of $11,977.80; therefore,
BE IT RESOLVED by the County Legislature of Jackson County, Missouri, that Change Order No. 1 (Final) to the aforesaid contract is approved and the Director of Public Works is authorized to execute the change order on behalf of the County; and,
BE IT FURTHER RESOLVED that the Director of the Department of Finance is authorized to make all payments, including final payment on the contract; and,
BE IT FURTHER RESOLVED that the Director of the Department of Finance is authorized to release the encumbrance on the contract balance.
Enacted and Approved
Effective Date: This Resolution shall be effective immediately upon its passage by a majority of the Legislature.
APPROVED AS TO FORM:
____________________________ ___________________________________
Acting Chief Deputy County Counselor County Counselor
Certificate of Passage
I hereby certify that the attached resolution, Resolution # 15327 of January 3, 2005 was duly passed on ____________January 3_...