File #: 13543    Version: 0 Name: Tapscott Road Bridge Replacement Project #2404
Type: Resolution Status: Passed
File created: 1/29/2001 In control: Public Works Committee
On agenda: 1/29/2001 Final action: 2/26/2001
Title: A RESOLUTION awarding a contract on Bid No. PW02-00 for the Tapscott Road Bridge Replacement Project, No. 2404 to Knapp Construction Company, Inc., of Kansas City, Kansas, in the actual amount of $194,391.50.
Sponsors: Bill Petrie
Indexes: CONTRACT, ROAD REHABILITATION
IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI


Title
A RESOLUTION awarding a contract on Bid No. PW02-00 for the Tapscott Road Bridge Replacement Project, No. 2404 to Knapp Construction Company, Inc., of Kansas City, Kansas, in the actual amount of $194,391.50.


Intro
RESOLUTION #13543, January 29, 2001

INTRODUCED BY Bill Petrie, County Legislator


Body
WHEREAS, the Director of Public Works has solicited formal written bids on Bid No. PW02_00 for the Tapscott Road Bridge Replacement Project, Number 2404; and,

WHEREAS, he has received as the lowest three bids thereon bids from the following:

VENDOR BID
R.A. Knapp Construction, Inc. $194,391.50
Kansas City, KS

Barcus and Son, Inc. $195,768.00
Kansas City, KS

Wiedenmann & Godfrey $213,800.00
Belton, MO

and,

WHEREAS, he has recommended that award be made to Knapp Construction Company, Inc., of Kansas City, KS, for the reason that it has submitted the lowest and best bid; therefore,

BE IT RESOLVED by the County Legislature of Jackson County, Missouri, that award be made as recommended by the Director of Public Works, and that the Director of Public Works be, and is hereby, authorized to execute for the County any documents necessary to the accomplishment of the award; and,

BE IT FURTHER RESOLVED that the Director of Public Works be and hereby is authorized to adjust contract line item quantities to the extent that no further financial obligation is thereby imposed on the County; and,

BE IT FURTHER RESOLVED that the Director of the Department of Finance is authorized to make all payments, except final payment on the contract.

Enacted and Approved
Effective Date: This Resolution shall be effective immediately upon its passage by a majority of the Legislature.

APPROVED AS TO FORM:

___________________________ ___________________________
County Counselor

Certificate of Passage
...

Click here for full text