Title: A RESOLUTION awarding a contract on Bid No. PW 08-2011 for the Argo Road Culvert Repairs, Corn Road Bridge Repairs, and Park Trail Repair, Project Nos. 3144, 3145, and 3149, to KAT Excavation, Inc., of Bates City, MO, at an actual cost to the County not to exceed $167,002.00, and authorizing the Director of Public Works to approve line item adjustments under this contract at no additional cost to the County.
Sponsors: Bob Spence
Indexes: ARGO ROAD CULVERT REPAIRS, PUBLIC WORKS
Attachments: 1. 17691adopt.pdf
IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI

Title
A RESOLUTION awarding a contract on Bid No. PW 08-2011 for the Argo Road Culvert Repairs, Corn Road Bridge Repairs, and Park Trail Repair, Project Nos. 3144, 3145, and 3149, to KAT Excavation, Inc., of Bates City, MO, at an actual cost to the County not to exceed $167,002.00, and authorizing the Director of Public Works to approve line item adjustments under this contract at no additional cost to the County.

Intro
RESOLUTION #17691, October 10, 2011

INTRODUCED BY Bob Spence, County Legislator


Body
WHEREAS, two culverts located on Argo Road, one bridge located on Corn Road, and a section of trail in the Blue Springs Lake Park are in need of repairs; and,

WHEREAS, the Director of Public Works has solicited formal written bids on Bid No. 08-2011 for Argo Road Culvert Repairs, Corn Road Bridge Repairs, and Park Trail Repair, Project Nos. 3144, 3145, and 3149; and,

WHEREAS, the Director of Public Works has received ten bids thereon, with the three lowest bids as follows:

VENDOR BID

KAT Excavation, Inc.
Bates City, MO $167,002.00

Leath and Sons Construction
Raytown, MO $177,825.00

Wil-Pav, Inc.
Sugar Creek, MO $197,463.00

and,

WHEREAS, the Director of Public Works recommends that award be made to KAT Excavation, Inc., for the reason that it has submitted the lowest and best bid; and,

WHEREAS, in the event that line item adjustments to the contract become necessary, it is appropriate that the Director of Public Works be authorized to approve said line item adjustments to the extent there is no additional cost to the County; now therefore,

BE IT RESOLVED by the County Legislature of Jackson County, Missouri, that award be made as recommended by the Director of Public Works, and that the Director be and hereby is authorized to execute any documents necessary to the accomplishment of the award; and,

BE IT FURTHER RESOLVED that ...