IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI
Title
A RESOLUTION authorizing the County Executive to execute Change Order No. 1 to the contract awarded to GameTime c/o Cunningham Associates, Inc., of Charlotte, North Carolina, for the design and installation of playground areas at various shelter locations in Lake Jacomo at a cost to the County not to exceed $4,431.10 for a new total cost not to exceed $191,461.00.
Intro
RESOLUTION # 15514, June 13, 2005
INTRODUCED BY Fred Arbanas, County Legislator
Body
WHEREAS, by Resolution 15106, the County Legislature did approve a contract with GameTime c/o Cunningham Associates, Inc., of Charlotte, North Carolina, for the design and installation of playground areas at various shelter locations in Lake Jacomo; and,
WHEREAS, Change Order No. 1 is required to cover the cost for removal of rock encountered by the contractor during the installation of play equipment at Shelters 1 and 2; now therefore,
BE IT RESOLVED by the County Legislature of Jackson County, Missouri, that Change Order No. 1 to the aforesaid contract be and hereby is approved and that County Executive be and hereby is authorized to execute Change Order No. 1 on behalf of the County; and,
BE IT FURTHER RESOLVED that the Manager of the Division of Finance is authorized to make all payments, including final payment on the contract.
Enacted and Approved
Effective Date: This Resolution shall be effective immediately upon its passage by a majority of the Legislature.
APPROVED AS TO FORM:
______________________________ ________________________________
Acting Chief Deputy County Counselor County Counselor
Certificate of Passage
I hereby certify that the attached resolution, Resolution # 15514 of June 13, 2005, was duly passed on __________June 20_________________, 2005 by the Jackson County Legislature. The votes thereon were as follows:
Yeas ________7_________ Nays _...