Title: A RESOLUTION awarding a term and supply contract on Bid No. 8-02 for the furnishing of pump maintenance for use by the Public Works and Parks and Recreation Departments to JCI Industries of Lee's Summit, MO, to provide for their needs for the upcoming one-year period, in the estimated amount of $20,000.00.
Sponsors: Bill Petrie
IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI

Title
A RESOLUTION awarding a term and supply contract on Bid No. 8-02 for the furnishing of pump maintenance for use by the Public Works and Parks and Recreation Departments to JCI Industries of Lee's Summit, MO, to provide for their needs for the upcoming one-year period, in the estimated amount of $20,000.00.


Intro
RESOLUTION #14048, March 4, 2002

INTRODUCED BY Bill Petrie, County Legislator


Body
WHEREAS, the Purchasing Director has solicited formal written bids on Bid No. 8-02 for the furnishing of pump maintenance for use by the Public Works and Parks and Recreation Departments to provide for their needs for the upcoming one_year period; and,

WHEREAS, he has received as the lowest three bids there on bids from the following:

VENDOR RATE PER HOUR
ON SITE

JCI Industries, Inc. $57.00
Lee's Summit, MO

Mid America $60.00
Kansas City, KS

Douglas Pump Service, Inc. $63.00
Overland Park, KS

and,
WHEREAS, the Purchasing Director has recommended that award be made JCI Industries of Lee's Summit, MO, for the reason that it has submitted the lowest and best bid; therefore,

BE IT RESOLVED by the County Legislature of Jackson County, Missouri, that award be made as recommended by the Purchasing Director, and that the Purchasing Director be, and is hereby, authorized to execute for the County any documents necessary to the accomplishment of the award; and,

BE IT FURTHER RESOLVED that the Director of the Department of Finance is authorized to make all payments, including final payment on the contract, to the extent sufficient appropriations to the using spending agencies have heretofore been made in the current Jackson County budget.

Enacted and Approved
Effective Date: This Resolution shall be effective immediately upon its passage by a majority of the Legislature.