IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI
Title
A RESOLUTION authorizing the County Executive to execute Change Order No. 4 (Final) to the contract with R. A. Knapp Construction of Kansas City, KS, for the Noland Road Bridge Replacement Project, No. 2390, adjusting all plan quantities to as-built quantities and decreasing the contract amount by $85,096.00.
Intro
RESOLUTION # 15408, March 7, 2005
INTRODUCED BY Bob Spence, County Legislator
Body
WHEREAS, the County did by Resolution 14800, dated November 23, 2003, enter into a contract on Bid No. PW 03-2003 with R. A Knapp Construction of Kansas City, KS, for the Noland Road Bridge Replacement Project, No. 2390, in the actual amount of $1,229,837.10; and,
WHEREAS, subsequent change orders authorized by Resolution 14913, dated February 17, 2004, and Resolution 15082, dated July 6, 2004, have increased the contract amount by $36,636.75 for a total current authorization of $1,266,473.85; and,
WHEREAS, Change Order No. 4 (Final), a copy of which is attached hereto and incorporated herein by reference, is necessary to make the final adjustments from plan quantities to as-built quantities and said change order will result in a decrease to the contract in the amount of $85,096.00; now therefore,
BE IT RESOLVED by the County Legislature of Jackson County, Missouri, that Change Order No. 4 (Final) to the aforesaid contract is hereby approved and that the County Executive is authorized to execute the change order on behalf of the County; and,
BE IT FURTHER RESOLVED that the Director of the Department of Finance be and hereby is authorized to make final payment and disencumber the contract balance of $85,096.00.
Enacted and Approved
Effective Date: This Resolution shall be effective immediately upon its passage by a majority of the Legislature.
APPROVED AS TO FORM:
____________________________ ______________________________
Acting Chief De...