File #: 12540    Version: 0 Name: Mechanical/plumbing system.
Type: Resolution Status: Passed
File created: 2/16/1999 In control: (R)Health and Justice Committee
On agenda: Final action: 2/22/1999
Title: A RESOLUTION authorizing Change Order No. 9 to the contract with Rodriguez Mechanical Contractors, Inc., of Overland Park, KS, (Bid No. PW-2345, Bid Package No. 6), for the construction and installation of mechanical and plumbing systems for the expansion at the Jackson County Detention Center, increasing the contract amount by $83,284.00.
Sponsors: Terry Young
Indexes: DETENTION CENTER
IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI

Title
A RESOLUTION authorizing Change Order No. 9 to the contract with Rodriguez Mechanical Contractors, Inc., of Overland Park, KS, (Bid No. PW-2345, Bid Package No. 6), for the construction and installation of mechanical and plumbing systems for the expansion at the Jackson County Detention Center, increasing the contract amount by $83,284.00.

Intro
RESOLUTION #12540, February 16, 1999

INTRODUCED BY Terry Young, County Legislator

Body
WHEREAS, the County did, by Resolution 11641, dated March 3, 1997, enter into a contract with Rodriguez Mechanical Contractors, Inc., of Overland Park, KS, in the actual amount of $2,431,360.00, and authorized additional expenditures approved by the County Executive at a cost not to exceed $116,000.00, for a total amount not to exceed $2,431,360.00, for the construction and installation of mechanical and plumbing systems for the expansion at the Jackson County Detention Center; and,

WHEREAS, the County Executive has approved Change Orders 1 through 8 for a total of $68,357.00, adjusting the contract amount to the current authorization of $2,499,717.00, leaving a balance of $47,643.00; and,

WHEREAS, the proposed Change Order No. 9, a copy of which is attached hereto and incorporated herein by reference, is necessary due to miscellaneous contract changes and additions, and said change order will result in an increase not to exceed $83,284.00; therefore,

BE IT RESOLVED by the County Legislature of Jackson County, Missouri, that Change Order No. 9 to the aforesaid contract is approved and the County Executive is authorized to execute the change order on behalf of the County; and,

BE IT FURTHER RESOLVED that the Director of the Department of Finance is authorized to make all payments, except final payment on the contract.
Attorney
Effective Date: This Resolution shall be effective immediately upon its passage by a majority of the Legislature.

...

Click here for full text