File #: 15598    Version: 0 Name: Tri-County Water Authority agreement - Colbern Road Phase II and III.
Type: Resolution Status: Passed
File created: 8/15/2005 In control: County Legislature
On agenda: 8/15/2005 Final action: 8/15/2005
Title: A RESOLUTION authorizing the County Executive to execute an Agreement with Tri-County Water Authority in conjunction with Colbern Road Phase II and III, Project Numbers 2411 and 2455.
Sponsors: Bob Spence
Indexes: COLBERN ROAD
IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI


Title
A RESOLUTION authorizing the County Executive to execute an Agreement with Tri-County Water Authority in conjunction with Colbern Road Phase II and III, Project Numbers 2411 and 2455.

Intro
RESOLUTION # 15598, August 15, 2005

INTRODUCED BY Bob Spence, County Legislator


Body

WHEREAS, the Director of Public Works recommends a proposed Agreement with Tri-County Water Authority ("Tri-County") in which the County will be able to access easements for project construction for the Colbern Road Phase II and III, Project Number 2411 and 2455; and,

WHEREAS, as part of that agreement the Tri-County Water Authority will pay the County the sum of $54,510.00 for the County's budgeted and anticipated cost of relocating and reconstructing Tri-County's water main within thirty (30) days after the County has accepted a relocation bid for the water main and any funds received therefrom will be appropriated by ordinance; and,

WHEREAS, the proposed agreement provides that if an approved change order increases the cost of the relocation of the water main, Tri-County shall pay the additional costs within thirty (30) days after approval of the change order; and,

WHEREAS, the Director of Public Works requests authorization to adjust any contract line item quantities to the extent that there will be no further funding obligation by the County in order to fully utilize budgeted funds without the necessity of seeking legislative review of minor change order details; now therefore,

BE IT RESOLVED by the County Legislature of Jackson County, Missouri, that the County Executive be and hereby is authorized to execute the proposed Agreement with Tri-County Water Authority in conjunction with the Colbern Road Phase II and III, Project Numbers 2411 and 2455 in a form to be approved by the County Counselor; and,

BE IT FURTHER RESOLVED that the Director of Public Works be and hereby is authorized ...