Title: A RESOLUTION awarding a contract for the repair and rehabilitation of a sanitary sewer line for use by the Parks and Recreation Department to Insituform Technologies USA, Inc., of Chesterfield, Missouri, under the terms and conditions of the City of Independence Contract No. 282-10, an existing government contract, at an actual cost to the County not to exceed $47,377.26.
Sponsors: Fred Arbanas
Indexes: PARKS + RECREATION, REPAIRS/IMPROVEMENTS, SEWER LINE
Attachments: 1. 17857adopt.pdf
      IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI
 
 
Title
A RESOLUTION awarding a contract for the repair and rehabilitation of a sanitary sewer line for use by the Parks and Recreation Department to Insituform Technologies USA, Inc., of Chesterfield, Missouri, under the terms and conditions of the City of Independence Contract No. 282-10, an existing government contract, at an actual cost to the County not to exceed $47,377.26.
 
 
Intro
RESOLUTION #17857, March 19, 2012
 
INTRODUCED BY Fred Arbanas, County Legislator
 
Body
WHEREAS, the Parks and Recreation Department is in need of the repair and rehabilitation of the sanitary sewer line located at the Jacomo Campground at Fleming Park; and,
 
WHEREAS, the Director of Finance and Purchasing recommends the award of a contract for this repair to Insituform Technologies USA, Inc., of Chesterfield, Missouri, under the terms and conditions of City of Independence Contract No. 282-10, an existing government contract, at an actual cost to the County not to exceed $47,377.26; and,
 
WHEREAS, the Director recommends award under section 1030.4, Jackson County Code, 1984, for the reason that this will allow the County to take advantage of discounts offered to large entities; now therefore,
 
BE IT RESOLVED that award be made under the existing government contract as recommended by the Director of Finance and Purchasing and that the Director be, and is hereby, authorized to execute for the County any documents necessary for the accomplishment of the award; and,
 
BE IT FURTHER RESOLVED that the Director of Finance and Purchasing be and hereby is authorized to make all payments, including final payment on the contract.
 
Enacted and Approved
Effective Date: This Resolution shall be effective immediately upon its passage by a majority of the Legislature.
 
APPROVED AS TO FORM:
 
____________________________              ________________________________
Chief Deputy County Counselor                   County Counselor
 
 
Certificate of Passage
 
      I hereby certify that the attached resolution, Resolution #17857 of March 19, 2012, was duly passed on _______________________________, 2012 by the Jackson County Legislature.  The votes thereon were as follows:
 
 
            Yeas _________________      Nays _____________
 
            Abstaining _____________      Absent ____________
 
 
______________________              _________________________________
Date                                    Mary Jo Spino, Clerk of Legislature
 
Fiscal Note
There is a balance otherwise unencumbered to the credit of the appropriation to which the expenditure is chargeable and there is a cash balance otherwise unencumbered in the treasury to the credit of the fund from which payment is to be made each sufficient to provide for the obligation herein authorized.
 
 
ACCOUNT NUMBER:      300      1608      58060
ACCOUNT TITLE:            Park Enterprise Fund
                        Parks - Construction Services
                        Other Improvements
NOT TO EXCEED:            $47,378.00
 