File #: 13472    Version: 0 Name: Decrease in contract with Tasco Construction.
Type: Resolution Status: Passed
File created: 12/11/2000 In control: Public Works Committee
On agenda: 12/11/2000 Final action: 12/18/2000
Title: A RESOLUTION authorizing Change Order No. 2 (Final) to the contract with Tasco Construction of Pleasant Hill, MO, for the Buckner Tarsney Road @ Hammond Road Projects, Nos. 2354 and 2395, decreasing the contract amount by $43,731.22.
Sponsors: Bill Petrie
Indexes: CHANGE ORDER

IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI

 

 

Title

A RESOLUTION authorizing Change Order No. 2 (Final) to the contract with Tasco Construction of Pleasant Hill, MO, for the Buckner Tarsney Road @ Hammond Road Projects, Nos. 2354 and 2395, decreasing the contract amount by $43,731.22.

 

 

Intro

RESOLUTION #13472, December 11, 2000

 

INTRODUCED BY Bill Petrie, County Legislator

 

 

Body

WHEREAS, the County did, by Resolution 12826, dated August 2, 1999, enter into a contract with Tasco Construction of Pleasant Hill, MO, in the actual amount of $581,118.22, for the Buckner Tarsney Road @ Hammond Road Projects, No. 2354 and No. 2395; and,

 

WHEREAS, a previous change order has adjusted the contract price to its current authorization of $636,109.22; and,

 

 WHEREAS, the proposed Change Order No. 2 (Final), a copy of which is attached hereto and incorporated herein by reference, is necessary to adjust various plan quantities to as-built quantities and will decrease the contract amount by $43, 731.22, for a final amount of $592,378.00; therefore,

 

BE IT RESOLVED by the County Legislature of Jackson County, Missouri, that Change Order No. 2 to the aforesaid  contract be, and is hereby, approved and the Director of Public Works be, and is hereby authorized to execute the said change order on behalf of the County; and,

 

BE IT FURTHER RESOLVED that the Director of the Department of Finance be and hereby is authorized to make all payments, including final payment on the contract; and,

 

BE IT FURTHER RESOLVED that the Manager of the Division of Finance be and hereby is authorized to release the balance of the encumbrance on this contract.

 

Enacted and Approved

Effective Date:  This Resolution shall be effective immediately upon its passage by a majority of the Legislature.

 

 

APPROVED AS TO FORM:

 

 

____________________________                       ___________________________________

                                                                                                                                                                        County Counselor

 

Certificate of Passage

 

                     I hereby certify that the attached resolution, Resolution #13472 of December 11, 2000  was duly passed on ____________December 19______________________, 2000 by the Jackson County Legislature.  The votes thereon were as follows:

 

 

                     Yeas _______9__________          Nays ______0________

 

                     Abstaining ______0_______                            Absent ______0______

 

 

 

______________________                       _____________________________________

Date                                                                                                                              Mary Jo Brogoto, Clerk of Legislature