File #: 15705    Version: 0 Name: Contract with J.M. Fahey Construction - Harry Truman Drive Extension Project.
Type: Resolution Status: Passed
File created: 11/21/2005 In control: Public Works Committee
On agenda: 11/21/2005 Final action: 11/28/2005
Title: A RESOLUTION awarding a contract on Bid No.PW01-2005 to J.M. Fahey Construction Company of Grandview, MO, for the Harry Truman Drive Extension Project #2999, at a cost to the County not to exceed $2,325,027.13.
Sponsors: Bob Spence
Indexes: HARRY S TRUMAN DRIVE

                       IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI

 

Title

A RESOLUTION awarding a contract on Bid No.PW01-2005 to J.M. Fahey Construction Company of Grandview, MO, for the Harry Truman Drive Extension Project #2999, at a cost to the County not to exceed $2,325,027.13.

 

Intro

RESOLUTION # 15705, November 21, 2005

INTRODUCED BY Bob Spence, County Legislator

 

Body

WHEREAS, by Resolution No. 14853, dated January 5, 2004, the Legislature did designate the improvement of Harry S. Truman Drive between 125th Street and Crystal Avenue as a County Urban Road System priority within the City of Grandview; and,

 

WHEREAS, pursuant to a Cooperative Agreement between the County and the City of Grandview, MO, the Director of Public Works solicited formal written bids under Bid No. PW01-2005 for the Harry Truman Drive Extension Project, #2999; and,

 

WHEREAS, he has received as the three lowest bids, bids from the following:

                     VENDOR                                                                                                                                                   COST

                     J.M. Fahey Construction Co.                                                                                    $2,325,027.13

                     Grandview, MO

 

                     L.B. Enterprizes Inc.                                                                                                                              $2,380,000.00

                     Belton, MO

                     

                     Leavenworth Excavating & Equip. Co.,                                                               $2,703,857.05

                     Leavenworth, KS

and,

 

WHEREAS, the Director of Public Works recommends that the contract award be made to J.M. Fahey Construction Co., of Grandview, MO, for the Harry Truman Drive Extension Project #2999 at a cost to the County not to exceed $2,325,027.13; now therefore,

 

BE IT RESOLVED by the County Legislature of Jackson County, Missouri that the award be made as recommended and that the County Executive be and hereby is authorized to execute any and all documents necessary to the accomplishment of the award; and,

 

BE IT FURTHER RESOLVED that the Director of the Department of Finance is authorized to make all payments, except final payment, on the contract; and,

 

BE IT FURTHER RESOLVED that the Director of Public Works be and hereby is authorized to approved adjustments in the contract line items, to the extent that no further obligation on the County is thereby created.

 

 

Enacted and Approved

Effective Date:  This Resolution shall be effective immediately upon its passage by a majority of the Legislature.

 

APPROVED AS TO FORM:

____________________________                                              ______________________________

Chief Deputy County Counselor                                                                                    County Counselor

 

Certificate of Passage

                     I hereby certify that the attached resolution, Resolution # 15705 of November 21, 2005 was duly passed on ____________November 28________________, 2005 by the Jackson County Legislature.  The votes thereon were as follows:

 

                     Yeas _______9________                                                               Nays ______0________

                     Abstaining ____0_____                                                               Absent ____0________

 

________________________                                                               ____________________________

Date                                                                                                                                                   Mary Jo Spino, Clerk of Legislature

 

 

Fiscal Note

                                                               

Subject to appropriation of the 2006 Budget.

 

 

 

_______________________                                            __________________________________