File #: 15545    Version: 0 Name: Temporary construction easement, Colbern Road Phase II Project.
Type: Resolution Status: Passed
File created: 6/27/2005 In control: Public Works Committee
On agenda: 6/27/2005 Final action: 7/11/2005
Title: A RESOLUTION accepting a temporary construction easement and authorizing payment to the property owner trustees Clark and Terri Gundersen, in the total amount of $24,738.70 for the Colbern Road Phase II Project.
Sponsors: Bob Spence
Indexes: EASEMENTS

IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI

 

Title

 

A RESOLUTION accepting a temporary construction easement and authorizing payment to the property owner trustees Clark and Terri Gundersen, in the total amount of $24,738.70 for the Colbern Road Phase II Project.

 

Intro

 

RESOLUTION # 15545,   June 27, 2005

 

INTRODUCED BY Bob Spence, County Legislator

 

Body

 

WHEREAS, the County has a need for a temporary construction easement for the widening of Colbern Road, Phase II Project; and,

 

WHEREAS, the owners of the property have agreed to convey the necessary temporary construction easement to the County as set forth in Exhibit "A"; and,

 

WHEREAS, the Director of the Department of Public Works recommends acceptance of the temporary construction easement; and,

 

WHEREAS, it is also the recommendation of the Director of Public Works to pay a lump sum amount of $24,738.70 to Clark Gundersen and Terri Gundersen as trustees for the temporary construction easement; now therefore,

 

BE IT RESOLVED  by the County Legislature of Jackson County, Missouri, that the  aforementioned temporary construction easement, further described in the attached "Exhibit A", be and hereby is accepted and that the Manager of Finance be and hereby is directed to issue a lump sum payment in the amount of $24,738.70 to Clark Gundersen and Terri Gundersen, Trustees of the  Clark Gundersen and Terri Gundersen Living Trust in consideration for said easement.

 

 

 

 

Enacted and Approved

Effective Date:  This Resolution shall be effective immediately upon its passage by a majority of the Legislature.

 

APPROVED AS TO FORM:

 

______________________________     _________________________________

Acting Chief Deputy County Counselor                         County Counselor                                           

 

Certificate of Passage

 

     I hereby certify that the attached resolution, Resolution # 15545, June 27, 2005  was duly passed on __________July 11_________________, 2005 by the Jackson County Legislature.  The votes thereon were as follows:

 

                           Yeas ________8_________                      Nays _______0_______

 

                           Abstaining ______0_______                     Absent _____1_______

 

 

______________________                                            _________________________________

Date                                                                                                                              Mary Jo Spino, Clerk of Legislature

 

Fiscal Note

 

There is a balance otherwise unencumbered to the credit of the appropriation to which the expenditure is chargeable and there is a cash balance otherwise unencumbered in the treasury to the credit of the fund from which payment is to be made each sufficient to provide for the obligation herein authorized.

 

ACCOUNT NUMBER:                      400-1544-8070

 

ACCOUNT TITLE:                                          CURS

                                                                                    City of Lee's Summit                     

                                                                                    City Projects

 

NOT TO EXCEED:                                          $24,738.70

 

 

 

________________________                          __________________________________

Date                                                                                                             Director of the Department of Finance