IN THE COUNTY LEGISLATURE OF JACKSON COUNTY, MISSOURI
Title
A RESOLUTION awarding a contract on Bid No. PW 01-2021 for the 2021 Pavement Maintenance Project (Phase 1, Asphaltic Concrete Overlay), Project No. 3248, to Superior Bowen Asphalt Co., LLC, of Kansas City, MO, at an actual cost to the County in the amount of $1,594,022.00, and authorizing the Director of Public Works to approve line item adjustments under this contract at no additional cost to the County.
Intro
RESOLUTION NO. 20677, May 17, 2021
INTRODUCED BY Theresa Cass Galvin, County Legislator
Body
WHEREAS, the Director of Public Works has solicited formal written bids on Bid No. PW 01-2021 for the 2021 Pavement Maintenance Project (Phase 1, Asphaltic Concrete Overlay), Project No. 3248, for use by the Public Works Department; and,
WHEREAS, notifications were distributed through advertisement and online posting and two responses were received from the following:
BIDDER BID AMOUNT
Superior Bowen Asphalt Co., LLC $1,594,021.10
Kansas City (Jackson County), MO
Ideker, Inc. $1,680,075.75
St. Joseph, MO
and,
WHEREAS, the Director of Public Works recommends the award of the contract to Superior Bowen Asphalt Co., LLC, for the reason that it has submitted the lowest and best bid; and,
WHEREAS, in the event that line item adjustments to the contract become necessary, it is appropriate that the Director of Public Works be authorized to approve said line item adjustments to the extent there is no additional cost to the County; now therefore,
BE IT RESOLVED by the County Legislature of Jackson County, Missouri, that award be made as recommended by the Director of Public Works and that the Director be and hereby is authorized to execute any documents necessary to the accomplishment of the award; and,
BE IT FURTHER RESOLVED that the Director of Public Works be and hereby is authorized to make adjustments in the contract line item quantities to the extent that there will be no further funding obligation to the County; and,
BE IT FURTHER RESOLVED that the Director of Finance and Purchasing is authorized to make all payments, including final payment on the contract.
Enacted and Approved
Effective Date: This Resolution shall be effective immediately upon its passage by a majority of the Legislature.
APPROVED AS TO FORM:
____________________________ _____________________________
Chief Deputy County Counselor County Counselor
Certificate of Passage
I hereby certify that the attached resolution, Resolution No. 20677 of May 17, 2021, was duly passed on May 24, 2021 by the Jackson County Legislature. The votes thereon were as follows:
Yeas ______8_________ Nays ______0________
Abstaining _____0______ Absent _____1_______
________________________ ______________________________
Date Mary Jo Spino, Clerk of Legislature
Fiscal Note
There is a balance otherwise unencumbered to the credit of the appropriation to which the expenditure is chargeable and there is a cash balance otherwise unencumbered in the treasury to the credit of the fund from which payment is to be made each sufficient to provide for the obligation herein authorized.
ACCOUNT NUMBER: 004 1506 58040
ACCOUNT TITLE: Special Road and Bridge Fund
Road & Bridge Maintenance
Roads & Highways
NOT TO EXCEED: $1,522,719.00
ACCOUNT NUMBER: 003 1608 58060
ACCOUNT TITLE: Park Fund
Construction Services
Other Improvements
NOT TO EXCEED: $71,303.00
_______________________ _______________________________
Date Chief Administrative Officer